- Assembly and welding of Main-Steam Form Pieces. (2008 to 2011).
SASOL I:
- Pre-fabrication of Piping Spool Pieces for the Wax Plant Upgrade. (2012).
OPTIMUM COLLIERY, Jormid:
- Welded repairs to Dragline Core Booms, Refurbishment of Dragline Tub.
ESKOM KUSILE, Dynamic Instruments. (ABB):
- Welding of Instrumentation Piping.
ESKOM MATLA, Dynamic Instruments:
- Fabrication of HP & LP Heater Branching units.
ESKOM MATLA, Dynamic Instruments:
- Re-routing of instrumentation line refurbishment. (2012 & currently on the third unit).
Steinmüller Africa (Manufacturing PTA Works):
- Fabrication of both the Medupi and Kusile Re-Heater inlet & outlet tube bundles(2011 & 2012), Fabrication of the Duvha Burner Mouth Openings Assemblies - 33 Units. (2012-2014).
Steval Engineering:
- Fabrication of casting liner plates.
Andritz:
- Fabrication and refurbishment of “Decanter / Centrifuge” (2012 and ongoing).
Babak Steam Services:
- Re-tubing of 3 off John Thompson Fire Tube Boiler. (2011).
Evraz Highveld Steel & Vanadium:
- BOF Hood Replacement, Lance Opening Replacement, Flue gas ducting replacement, Ongoing maintenance and repair work. Design, Supply, fabricate and install, Ø 200 NB sch 40 X 200 meters long 0xygen line and tie into existing 0xygen pipe line.
ESKOM LETHABO Power Station:
- Quality control services for boiler internals for 12 outages during a three year period.
ESKOM MATLA:
- The onsite Hydrostatic Pressure testing Unit three’s LP Heaters 1 & 2.
ESKOM MATLA:
- Process Projects - Supply, site assembly and fabrication of the acid dossing plant.
ESKOM KUSILE: Power Station New build:
- Murray & Roberts Projects, site assembly and fabrication of the boiler walls.(2012-2018).
- HAH Super-heater Vertical boiler walls, Units two to six HAD Evaporator Spiral boiler walls, Units one to six.
ESKOM KUSILE: Endel Engie:
- Installation and erection of mechanical equipment as well as welded and connected piping on the Turbine Hall Unit 3. (2014-2016).
Omnia Fertilizers:
- General on-site maintenance work.
Mondi Richards-bay, Clyde Bergemann Africa (Pty) Ltd:
- On site repair and maintenance to the boiler Soot Blowers, during a shut-down.
SAPPI Ngodwana Mill:
- Workshop fabrication of piping spool pieces with the onsite assembly and erection of the replacement boiler Soot Blower piping.
ESKOM Duvha Power Station:
- Unit 5 HP heaters repair leaking tubes, Unit 4 HP heaters repair leaking tubes.
ESKOM Gauteng Operating Unit:
- Supply and fabricate of Galvanised steel work for three years.
ESKOM Arnot Power Station: Hlakani Engineering Services:
- Replacement of Drain Valve at Unit 2 to Unit 6.
ESKOM Arnot Power Station: Steinmüller Africa:
- Install two off fuel oil platforms.
ESKOM MATLA: Dynamic Instruments:
- Manufacture Branching Units for Units 1 to 6.
ESKOM MATLA: Dynamic Instruments:
- Welding of Impulse piping for Units 2 to 6.
ESKOM KUSILE: Dynamic Instruments:
- New build, Welding of Impulse Piping for Unit 1.
SASOL: Steinmüller Africa:
- Manufacture of Sasol Wax Plant Pipe Spools.
ESKOM DUVHA, MAJUBA, KRIEL, MATLA, HENDRINA, ARNOT, CAMDEN, KRIEL, TUTUKA, Steinmüller Africa:
- Supervision and skills supply for Boiler Plant Maintenance. (1997-CURRENT).
ESKOM CAMDEN, GROOTVLEI, KOMATI, Steinmüller Africa:
- Supervision and skills supply for the Return to Service of these Power Stations.
ESKOM MATIMBA, Steinmüller Africa:
- Supply of Supervision and skills for HE Piping maintenance.